Q1: eqiad: (32) PDUs for expansion
Closed, ResolvedPublic

Description

This task will track the racking of the 32 new PDUs into the new eqiad row expansion.

8 cabinets of C2[LS]42CE-YCMFAM00 & 8 cabinets of C2[LS]54CE-YCMFA900 along with (16) PDU mounting brackets for Rittal racks.

The new row will likely be row E [1-8] and F [1-8] or just E [1-16].

The first 8 cabinets will get the C2[LS]42CE-YCMFAM00, the other 8 will get the C2[LS]54CE-YCMFA900 when they arrive in November.

Please note we aren't allowed to energize the PDUs, and must open a smart hands ticket with DC6 staff to do so. Once all 8 of the first racks are staged, a single ticket can be opened to have all 8 energized/plugged in.

Rack E1:

  • - receive in both C2[LS]42CE-YCMFAM00 and the mounting brackets via T286593, enter into Netbox.
  • - align the vertical rails in the cabinet to standard depths to allow full mounting of the PDUs and vertical cable managers.
  • - install C2[LS]42CE-YCMFAM00 into the rack - ensure the master and expansion PDUs are linked by the link cable included in the box. (silver ribbon cable, RJ type connector.)
  • - connect PDU to serial console server
  • - open ticket for PDUs to be plugged in / energized once racks E[1-8] are ready.
  • - confirm PDU energized for setup
  • - setup PDU according to directions on https://wikitech.wikimedia.org/wiki/SRE/Dc-operations/Platform-specific_documentation/ServerTech

Rack E2:

  • - receive in both C2[LS]42CE-YCMFAM00 and the mounting brackets via T286593, enter into Netbox.
  • - align the vertical rails in the cabinet to standard depths to allow full mounting of the PDUs and vertical cable managers.
  • - install C2[LS]42CE-YCMFAM00 into the rack - ensure the master and expansion PDUs are linked by the link cable included in the box. (silver ribbon cable, RJ type connector.)
  • - connect PDU to serial console server
  • - open ticket for PDUs to be plugged in / energized once racks E[1-8] are ready.
  • - confirm PDU energized for setup
  • - setup PDU according to directions on https://wikitech.wikimedia.org/wiki/SRE/Dc-operations/Platform-specific_documentation/ServerTech

Rack E3:

  • - receive in both C2[LS]42CE-YCMFAM00 and the mounting brackets via T286593, enter into Netbox.
  • - align the vertical rails in the cabinet to standard depths to allow full mounting of the PDUs and vertical cable managers.
  • - install C2[LS]42CE-YCMFAM00 into the rack - ensure the master and expansion PDUs are linked by the link cable included in the box. (silver ribbon cable, RJ type connector.)
  • - connect PDU to serial console server
  • - open ticket for PDUs to be plugged in / energized once racks E[1-8] are ready.
  • - confirm PDU energized for setup
  • - setup PDU according to directions on https://wikitech.wikimedia.org/wiki/SRE/Dc-operations/Platform-specific_documentation/ServerTech

Rack E4:

  • - receive in both C2[LS]42CE-YCMFAM00 and the mounting brackets via T286593, enter into Netbox.
  • - align the vertical rails in the cabinet to standard depths to allow full mounting of the PDUs and vertical cable managers.
  • - install C2[LS]42CE-YCMFAM00 into the rack - ensure the master and expansion PDUs are linked by the link cable included in the box. (silver ribbon cable, RJ type connector.)
  • - connect PDU to serial console server
  • - open ticket for PDUs to be plugged in / energized once racks E[1-8] are ready.
  • - confirm PDU energized for setup
  • - setup PDU according to directions on https://wikitech.wikimedia.org/wiki/SRE/Dc-operations/Platform-specific_documentation/ServerTech

Rack E5:

  • - receive in both C2[LS]42CE-YCMFAM00 and the mounting brackets via T286593, enter into Netbox.
  • - align the vertical rails in the cabinet to standard depths to allow full mounting of the PDUs and vertical cable managers.
  • - install C2[LS]42CE-YCMFAM00 into the rack - ensure the master and expansion PDUs are linked by the link cable included in the box. (silver ribbon cable, RJ type connector.)
  • - connect PDU to serial console server
  • - open ticket for PDUs to be plugged in / energized once racks E[1-8] are ready.
  • - confirm PDU energized for setup
  • - setup PDU according to directions on https://wikitech.wikimedia.org/wiki/SRE/Dc-operations/Platform-specific_documentation/ServerTech

Rack E6:

  • - receive in both C2[LS]42CE-YCMFAM00 and the mounting brackets via T286593, enter into Netbox.
  • - align the vertical rails in the cabinet to standard depths to allow full mounting of the PDUs and vertical cable managers.
  • - install C2[LS]42CE-YCMFAM00 into the rack - ensure the master and expansion PDUs are linked by the link cable included in the box. (silver ribbon cable, RJ type connector.)
  • - connect PDU to serial console server
  • - open ticket for PDUs to be plugged in / energized once racks E[1-8] are ready.
  • - confirm PDU energized for setup
  • - setup PDU according to directions on https://wikitech.wikimedia.org/wiki/SRE/Dc-operations/Platform-specific_documentation/ServerTech

Rack E7:

  • - receive in both C2[LS]42CE-YCMFAM00 and the mounting brackets via T286593, enter into Netbox.
  • - align the vertical rails in the cabinet to standard depths to allow full mounting of the PDUs and vertical cable managers.
  • - install C2[LS]42CE-YCMFAM00 into the rack - ensure the master and expansion PDUs are linked by the link cable included in the box. (silver ribbon cable, RJ type connector.)
  • - connect PDU to serial console server
  • - open ticket for PDUs to be plugged in / energized once racks E[1-8] are ready.
  • - confirm PDU energized for setup
  • - setup PDU according to directions on https://wikitech.wikimedia.org/wiki/SRE/Dc-operations/Platform-specific_documentation/ServerTech

Rack E8:

  • - receive in both C2[LS]42CE-YCMFAM00 and the mounting brackets via T286593, enter into Netbox.
  • - align the vertical rails in the cabinet to standard depths to allow full mounting of the PDUs and vertical cable managers.
  • - install C2[LS]42CE-YCMFAM00 into the rack - ensure the master and expansion PDUs are linked by the link cable included in the box. (silver ribbon cable, RJ type connector.)
  • - connect PDU to serial console server
  • - open ticket for PDUs to be plugged in / energized once racks E[1-8] are ready.
  • - confirm PDU energized for setup
  • - setup PDU according to directions on https://wikitech.wikimedia.org/wiki/SRE/Dc-operations/Platform-specific_documentation/ServerTech

Rack F1:

  • - receive in both C2[LS]42CE-YCMFAM00 and the mounting brackets via T286593, enter into Netbox.
  • - align the vertical rails in the cabinet to standard depths to allow full mounting of the PDUs and vertical cable managers.
  • - install C2[LS]42CE-YCMFAM00 into the rack - ensure the master and expansion PDUs are linked by the link cable included in the box. (silver ribbon cable, RJ type connector.)
  • - connect PDU to serial console server
  • - open ticket for PDUs to be plugged in / energized once racks E[9-16]/F[1-8] are ready.
  • - confirm PDU energized for setup
  • - setup PDU according to directions on https://wikitech.wikimedia.org/wiki/SRE/Dc-operations/Platform-specific_documentation/ServerTech

Rack F2:

  • - receive in both C2[LS]42CE-YCMFAM00 and the mounting brackets via T286593, enter into Netbox.
  • - align the vertical rails in the cabinet to standard depths to allow full mounting of the PDUs and vertical cable managers.
  • - install C2[LS]42CE-YCMFAM00 into the rack - ensure the master and expansion PDUs are linked by the link cable included in the box. (silver ribbon cable, RJ type connector.)
  • - connect PDU to serial console server
  • - open ticket for PDUs to be plugged in / energized once racks E[9-16]/F[1-8] are ready.
  • - confirm PDU energized for setup
  • - setup PDU according to directions on https://wikitech.wikimedia.org/wiki/SRE/Dc-operations/Platform-specific_documentation/ServerTech

Rack F3:

  • - receive in both C2[LS]42CE-YCMFAM00 and the mounting brackets via T286593, enter into Netbox.
  • - align the vertical rails in the cabinet to standard depths to allow full mounting of the PDUs and vertical cable managers.
  • - install C2[LS]42CE-YCMFAM00 into the rack - ensure the master and expansion PDUs are linked by the link cable included in the box. (silver ribbon cable, RJ type connector.)
  • - connect PDU to serial console server
  • - open ticket for PDUs to be plugged in / energized once racks E[9-16]/F[1-8] are ready.
  • - confirm PDU energized for setup
  • - setup PDU according to directions on https://wikitech.wikimedia.org/wiki/SRE/Dc-operations/Platform-specific_documentation/ServerTech

Rack F4:

  • - receive in both C2[LS]42CE-YCMFAM00 and the mounting brackets via T286593, enter into Netbox.
  • - align the vertical rails in the cabinet to standard depths to allow full mounting of the PDUs and vertical cable managers.
  • - install C2[LS]42CE-YCMFAM00 into the rack - ensure the master and expansion PDUs are linked by the link cable included in the box. (silver ribbon cable, RJ type connector.)
  • - connect PDU to serial console server
  • - open ticket for PDUs to be plugged in / energized once racks E[9-16]/F[1-8] are ready.
  • - confirm PDU energized for setup
  • - setup PDU according to directions on https://wikitech.wikimedia.org/wiki/SRE/Dc-operations/Platform-specific_documentation/ServerTech

Rack F5:

  • - receive in both C2[LS]42CE-YCMFAM00 and the mounting brackets via T286593, enter into Netbox.
  • - align the vertical rails in the cabinet to standard depths to allow full mounting of the PDUs and vertical cable managers.
  • - install C2[LS]42CE-YCMFAM00 into the rack - ensure the master and expansion PDUs are linked by the link cable included in the box. (silver ribbon cable, RJ type connector.)
  • - connect PDU to serial console server
  • - open ticket for PDUs to be plugged in / energized once racks E[9-16]/F[1-8] are ready.
  • - confirm PDU energized for setup
  • - setup PDU according to directions on https://wikitech.wikimedia.org/wiki/SRE/Dc-operations/Platform-specific_documentation/ServerTech

Rack F6

  • - receive in both C2[LS]42CE-YCMFAM00 and the mounting brackets via T286593, enter into Netbox.
  • - align the vertical rails in the cabinet to standard depths to allow full mounting of the PDUs and vertical cable managers.
  • - install C2[LS]42CE-YCMFAM00 into the rack - ensure the master and expansion PDUs are linked by the link cable included in the box. (silver ribbon cable, RJ type connector.)
  • - connect PDU to serial console server
  • - open ticket for PDUs to be plugged in / energized once racks E[9-16]/F[1-8] are ready.
  • - confirm PDU energized for setup
  • - setup PDU according to directions on https://wikitech.wikimedia.org/wiki/SRE/Dc-operations/Platform-specific_documentation/ServerTech

Rack F7:

  • - receive in both C2[LS]42CE-YCMFAM00 and the mounting brackets via T286593, enter into Netbox.
  • - align the vertical rails in the cabinet to standard depths to allow full mounting of the PDUs and vertical cable managers.
  • - install C2[LS]42CE-YCMFAM00 into the rack - ensure the master and expansion PDUs are linked by the link cable included in the box. (xsilver ribbon cable, RJ type connector.)
  • - connect PDU to serial console server
  • - open ticket for PDUs to be plugged in / energized once racks E[9-16]/F[1-8] are ready.
  • - confirm PDU energized for setup
  • - setup PDU according to directions on https://wikitech.wikimedia.org/wiki/SRE/Dc-operations/Platform-specific_documentation/ServerTech

Rack F8:

  • - receive in both C2[LS]42CE-YCMFAM00 and the mounting brackets via T286593, enter into Netbox.
  • - align the vertical rails in the cabinet to standard depths to allow full mounting of the PDUs and vertical cable managers.
  • - install C2[LS]42CE-YCMFAM00 into the rack - ensure the master and expansion PDUs are linked by the link cable included in the box. (silver ribbon cable, RJ type connector.)
  • - connect PDU to serial console server
  • - open ticket for PDUs to be plugged in / energized once racks E[9-16]/F[1-8] are ready.
  • - confirm PDU energized for setup
  • - setup PDU according to directions on https://wikitech.wikimedia.org/wiki/SRE/Dc-operations/Platform-specific_documentation/ServerTech

Event Timeline

RobH added a parent task: Unknown Object (Task).
RobH moved this task from Backlog to Racking Tasks on the ops-eqiad board.
wiki_willy renamed this task from Q2: eqiad: (32) PDUs for expansion to Q1: eqiad: (32) PDUs for expansion.Sep 13 2021, 10:38 PM

Netbox Updates:

  • added network port to all ps1-[ef]-eqiad
  • added power ports (54 or 42 depending on model) to all ps[12]-[ef]-eqiad

Added in the IP addresses in the mgmt range that were available, and assigned them to the ps1-[ef]-eqiad with the following:

e1: 10.65.2.45/16
e2: 10.65.2.46/16
e3: 10.65.2.47/16
e4: 10.65.2.48/16
e5: 10.65.2.49/16
e6: 10.65.2.50/16
e7: 10.65.2.51/16
e8: 10.65.2.52/16

f1: 10.65.2.53/16
f2: 10.65.2.54/16
f3: 10.65.2.55/16
f4: 10.65.2.56/16
f5: 10.65.2.57/16
f6: 10.65.2.58/16
f7: 10.65.2.59/16
f8: 10.65.2.60/16

Ok, basic network and our PDU login applied to the admn user (need to setup root via https) all PDUs via SCS connections, next is connection via HTTPS for full configuration of snmp services.

PDUS in E1-E4 are fully setup with syslog, ntp, snmp settings. E5-E8 have their network setup done, but not their root user (admn only currently), snmp, ntp, or other settings done via https interface. Only [EF][1-4] have mgmt switches and the PDUs connected to mgmt network at this time.

Change 811382 had a related patch set uploaded (by Papaul; author: Papaul):

[operations/puppet@production] Add new PDU in row E Eqiad

https://gerrit.wikimedia.org/r/811382

Change 811382 merged by Papaul:

[operations/puppet@production] Add new PDU in row E Eqiad

https://gerrit.wikimedia.org/r/811382

Change 870975 had a related patch set uploaded (by RobH; author: RobH):

[operations/puppet@production] adding pdus for racks f[1-4]

https://gerrit.wikimedia.org/r/870975

Change 870975 merged by RobH:

[operations/puppet@production] adding pdus for racks f[1-4]

https://gerrit.wikimedia.org/r/870975

pdu's have been connected to msw in rack and scs in f8. temp sensors are installed

@Jclark-ctr thanks i will start setting them up.

Change 902519 had a related patch set uploaded (by Papaul; author: Papaul):

[operations/puppet@production] Add new PDU's in row E-F[5-8]

https://gerrit.wikimedia.org/r/902519

Change 902519 merged by Papaul:

[operations/puppet@production] Add new PDU's in row E-F[5-8]

https://gerrit.wikimedia.org/r/902519

I setup the last 8 PDU's row E [4-8] and row F [4-8] but was not able to setup ps1-e8 ad ps1-f8 because of connectivity issue. I added those to librenms and icinga. so what left here to resolve this task is to fix the connectivity issue wih ps1-e8 and ps1-f8.
@Jclark-ctr can you please check those two PDU's next that you are on site?
Thanks

Papaul updated the task description. (Show Details)

This is complete