Jump to content

Shoaiba Power and Desalination Plant

Coordinates: 20°40′48″N 39°31′24″E / 20.680084°N 39.523233°E / 20.680084; 39.523233
From Wikipedia, the free encyclopedia
(Redirected from Shoaiba power station)

Shoaiba power and desalination plant
Map
CountrySaudi Arabia
Coordinates20°40′48″N 39°31′24″E / 20.680084°N 39.523233°E / 20.680084; 39.523233
Commission dateFebruary 2014
OwnerSaudi Consolidated Electric Company
OperatorSaudi Consolidated Electric Company
Thermal power station
Primary fuelFuel oil
Combined cycle?Yes
Power generation
Units operational14
Nameplate capacity5,600 MW

The Shoaiba power and desalination plant is an oil-fired, combined cycle gas turbine power and desalination complex in Saudi Arabia on the coast of Red Sea, about 120 kilometres (75 mi) south of Jeddah. It is one of the world's largest fossil fuel power plants, and the world's third largest integrated water and power plant.[1]

History

[edit]

The construction of the first plant 1 of the Shoaiba power station began in 1985 and second plant 2 1995 (although there was a power generation and saline desalination plant in operation at the site as far back as 1985 with commissioning support from Stuttgart-based Fichtner Consulting Engineers). The ABB-led consortium built a power station equipped with three turbines, heat recovery steam generators and ancillary power generation equipment. The first stage cost about US$850 million. The first unit came into operation in July 2001. The other two units were completed in August 2003. The contract for construction of the second stage was awarded to a consortium led by Alstom Power. A multi-stage flash distillation water desalination plant was built by Hanjung (now Doosan Heavy Industries) in partnership with Bechtel. The desalination plant of shoiaba phase 1 and phase 2 has a capacity of 76800 tons/day. 2017 awarded ph4 ro plant to doosan, started full production on 2020 February 384000 m3 per day.currently all three plants director Eng Abdur rahman al aofi.

Technical features

[edit]

After completing the third stage the power station consists of 14 units with a total capacity of 5,600 MW, which makes it one of the largest fossil fuel-fired power stations in the world. The last expansion was built by Alstom and is operational since 2012.[2] The oil for power production is supplied from Saudi Aramco by tankers.

The power station is connected to the 380 kV grid. The potable water is transferred via an 80 kilometres (50 mi) long water pipeline to the national water pipeline network. The power station provides the desalination facility with steam to heat the seawater distillers while reducing its own cooling demands.

Operating company

[edit]

The Shoaiba power station Saline Water Conversion Corporation is aided by the kingdom of Saudi Arabia and is monitored by the power and water ministry.

References

[edit]
  1. ^ "Milbank Makes it a One, Two, Three by Advising on Fujairah F2 IWPP, the World's Second Largest IWPP" (Press release). Milbank, Tweed, Hadley & McCloy. 18 December 2007. Archived from the original on 28 January 2013. Retrieved 23 October 2010.
  2. ^ Alstom: Alstom completes Shoaiba III power plant ahead of schedule
[edit]