Skagerrak (power transmission system)
Skagerrak | |
---|---|
Location | |
Country | Norway Denmark |
Coordinates | 58°15′36″N 7°53′55″E / 58.26000°N 7.89861°E 56°28′44″N 9°34′1″E / 56.47889°N 9.56694°E |
General direction | north–south–north |
From | Kristiansand (Norway) |
Passes through | Skagerrak |
To | Tjele (Denmark) |
Ownership information | |
Owner | Statnett Energinet |
Construction information | |
Manufacturer of conductor/cable | Alcatel Nexans Prysmian |
Manufacturer of substations | ABB |
Commissioned | 1977 |
Technical information | |
Type of current | HVDC |
Total length | 240 km (150 mi) |
Power rating | 1,632 MW (Skagerrak 1–4) |
No. of poles | 4 |
Skagerrak is the name of a 1,700 MW high-voltage direct current (HVDC) transmission facility between Tjele (Denmark) and Kristiansand (Norway). It is owned and operated by Statnett in Norway, and Energinet in Denmark.[1] The lines connect the hydroelectric-based Norwegian grid and the wind and thermal power-based Danish grid. In operation it enables more renewable energy in the energy mix, and more efficient use of electricity.[2]
Technical features
[edit]The 240-kilometre (150 mi) Skagerrak 1–3 scheme consists of a 113-kilometre (70 mi) overhead line and a 127-kilometre (79 mi) underwater cable.[1] It has a capacity of 1,050 megawatts (MW). Both land parts in Denmark and in Norway uses overhead lines from the cable landing point to the converter stations.[3] The overhead lines in Denmark are set to be renovated in 2016 for increased lifespan.[4] The towers were originally constructed for four poles, but were rebuilt for three conductors (three poles) when Skagerrak 3 was established. Near Aggersund HVDC Skagerrak crossed Aggersund strait overhead on 70-metre-tall (230 ft) towers with a 470-metre-long (1,540 ft) span, but were later converted to underground cables. The pylons of this span were the tallest electricity pylons of an HVDC line in Europe.
For such a long submarine cable, an AC transmission scheme would not be feasible since too much of the cable's capacity would be consumed by the capacitance of the cable itself, and the power systems in Norway and Jutland are not synchronous.
The transmission has a loss rate of 4%.[5]
The waste heat of the transformers is enough to supply district heating economically for 1,000 homes in nearby towns, but taxes prevent that project.[6] The adjacent Apple Datacenter (supplied in part by the Skagerrak cables via Tjele) was expected to work around the tax issue when supplying district heat to Viborg.[7]
Skagerrak 1 and 2
[edit]Skagerrak went in service in 1977 as a bipolar HVDC scheme. This facility was built with thyristor valves. When installed this underwater cable was the world's longest and deepest underwater HVDC power cable. The cable, manufactured by Alcatel, is laid in a maximum water depth of 530 metres (1,740 ft).[8]
Both cables have a capacity of 250 MW at 250 kV.[1]
Skagerrak 3
[edit]In 1993 the scheme was extended by HVDC Skagerrak 3. Skagerrak 3 is a monopolar line for a voltage of 350 kV with a capacity of 440 MW at 350 kV.[1] In installing Skagerrak 3, the old poles Skagerrak 1 and Skagerrak 2 were converted to monopolar HVDC schemes, which run with opposite polarity to Skagerrak 3.[3] In 1999, the full 1,000 MW capacity was reserved by large power companies.[9]
Skagerrak 4
[edit]In November 2009, Statnett and Energinet.dk signed the agreement to construct Skagerrak 4.[10][11] The capacity of Skagerrak 4 is approximately 700 MW with a DC voltage of 500 kV.[12] It had been in a test phase since 1 October 2014 and became operational at the end of 2014, when strong winds created negative prices despite the new connection.[13] It was officially inaugurated by Frederik, Crown Prince of Denmark and Haakon, Crown Prince of Norway on 12 March 2015.[14] As for the existing Skagerrak 1-3, the grid connection points are Kristiansand and Tjele. Differently from Skagerrak 1–3, for Skagerrak 4 a cable solution is chosen for the complete route length.[1] The 300 million DKK Prysmian land cable on the Danish side is approximately 90 kilometres (56 mi), while the 137 kilometres (85 mi) subsea cable and the 12 kilometres (7.5 mi) Norwegian land cable is to be made by Nexans for 638 million DKK.[15] Converter stations were built by ABB, as for Skagerrak 1–3.[16] The combined budget is 2.8-3.2 billion DKK.[15][17]
The technology used was VSC, capable of black start. Although thyristor-based converters have a loss of only 0.7%, the IGBTs of VSC get close with a loss of 0.8 to 1%. Skagerrak 1 and 2 previously used Skagerrak 3 as a return cable, but 1 and 2 were again coupled so that Skagerrak 4 can use number 3 for returns.[18] The cable also supplies 110 MW of reserve power.[19] Some of the 24 fiber pairs may be rented for business by telecommunications companies.[20]
Sites
[edit]Site | Coordinates |
---|---|
Tjele HVDC Static Inverter | 56°28′44″N 9°34′1″E / 56.47889°N 9.56694°E |
Denmark Overhead Electrode Line Terminal | 56°37′16″N 9°28′32″E / 56.62111°N 9.47556°E |
Aggersund Crossing Tower South | 57°0′0″N 9°18′7″E / 57.00000°N 9.30194°E |
Aggersund Crossing Tower North | 57°0′12″N 9°17′50″E / 57.00333°N 9.29722°E |
Danish Cable Terminal | 57°7′34″N 9°3′58″E / 57.12611°N 9.06611°E |
Norway Cable Terminal | 58°7′45″N 8°10′3″E / 58.12917°N 8.16750°E |
Norway Electrode Line Terminal | 58°10′02″N 8°15′56″E / 58.16722°N 8.26556°E |
Norway Electrode Line Branch | 58°11′10″N 8°9′24″E / 58.18611°N 8.15667°E |
Kristiansand HVDC Static Inverter | 58°15′36″N 7°53′55″E / 58.26000°N 7.89861°E |
Waypoints
[edit]- Overhead line in Denmark
- 56°28′46″N 9°33′57″E / 56.479315°N 9.565895°E
- 56°28′52″N 9°33′23″E / 56.481149°N 9.556266°E
- 56°31′20″N 9°29′26″E / 56.522125°N 9.490675°E
- 56°33′30″N 9°28′23″E / 56.558318°N 9.472951°E
- 56°34′55″N 9°28′06″E / 56.582026°N 9.468273°E
- 56°36′01″N 9°28′24″E / 56.600344°N 9.473198°E
- 56°37′16″N 9°28′33″E / 56.621169°N 9.475719°E
- 56°38′13″N 9°30′45″E / 56.637062°N 9.512615°E
- 56°39′06″N 9°31′06″E / 56.651797°N 9.518441°E
- 56°40′09″N 9°31′09″E / 56.669172°N 9.519305°E
- 56°41′24″N 9°32′00″E / 56.69005°N 9.533397°E
- 56°42′21″N 9°31′46″E / 56.70589°N 9.529567°E
- 56°45′47″N 9°29′28″E / 56.762998°N 9.491029°E
- 56°46′59″N 9°28′55″E / 56.782921°N 9.481995°E
- 56°49′21″N 9°25′25″E / 56.822549°N 9.423673°E
- 56°52′27″N 9°22′19″E / 56.874104°N 9.371949°E
- 56°54′49″N 9°20′16″E / 56.913653°N 9.337843°E
- 56°55′52″N 9°20′23″E / 56.931020°N 9.33972°E
- 56°57′58″N 9°19′50″E / 56.965994°N 9.330504°E
- 56°59′13″N 9°18′32″E / 56.987038°N 9.308993°E
- 56°59′49″N 9°18′22″E / 56.997079°N 9.306085°E
- 57°00′23″N 9°17′36″E / 57.006387°N 9.293393°E
- 57°01′30″N 9°16′21″E / 57.025084°N 9.272568°E
- 57°03′33″N 9°09′58″E / 57.059085°N 9.166085°E
- 57°07′12″N 9°04′21″E / 57.120022°N 9.072508°E
- 57°07′20″N 9°04′08″E / 57.122346°N 9.068903°E
- 57°07′34″N 9°03′58″E / 57.126189°N 9.066135°E
- Underground cable in Denmark
- 57°07′34″N 9°03′58″E / 57.126207°N 9.066178°E
- 57°07′59″N 9°03′06″E / 57.133043°N 9.051790°E
- 57°08′17″N 9°02′50″E / 57.138114°N 9.047198°E
- 57°08′37″N 9°02′52″E / 57.143504°N 9.047906°E
- 57°09′11″N 9°03′16″E / 57.152950°N 9.054419°E
- Overhead line in Norway
- 58°07′45″N 8°10′04″E / 58.129169°N 8.167713°E
- 58°07′49″N 8°10′02″E / 58.130359°N 8.167219°E
- 58°07′51″N 8°09′43″E / 58.130820°N 8.161973°E
- 58°08′00″N 8°09′29″E / 58.133253°N 8.157971°E
- 58°08′13″N 8°09′27″E / 58.136991°N 8.157617°E
- 58°08′31″N 8°09′25″E / 58.142026°N 8.157048°E
- 58°09′33″N 8°09′16″E / 58.159212°N 8.154495°E
- 58°10′42″N 8°09′43″E / 58.178284°N 8.161898°E
- 58°11′10″N 8°09′25″E / 58.185999°N 8.157005°E
- 58°11′39″N 8°08′45″E / 58.194137°N 8.148634°E
- 58°13′03″N 8°07′45″E / 58.217466°N 8.129132°E
- 58°13′30″N 8°07′39″E / 58.225054°N 8.127528°E
- 58°13′55″N 8°06′04″E / 58.231935°N 8.101022°E
- 58°13′49″N 8°05′07″E / 58.230234°N 8.085262°E
- 58°13′38″N 8°04′25″E / 58.227336°N 8.073497°E
- 58°13′26″N 8°02′15″E / 58.223947°N 8.037486°E
- 58°13′11″N 8°01′14″E / 58.219686°N 8.020642°E
- 58°13′08″N 8°00′24″E / 58.218983°N 8.006635°E
- 58°13′21″N 7°58′15″E / 58.222500°N 7.970731°E
- 58°13′42″N 7°56′17″E / 58.228240°N 7.937998°E
- 58°13′57″N 7°55′12″E / 58.232483°N 7.919941°E
- 58°14′54″N 7°54′50″E / 58.248283°N 7.913911°E
- 58°15′20″N 7°54′43″E / 58.255476°N 7.911841°E
- 58°15′31″N 7°54′22″E / 58.258586°N 7.906154°E
- 58°15′39″N 7°54′12″E / 58.260787°N 7.903225°E
- 58°15′40″N 7°54′03″E / 58.261018°N 7.900715°E
- Electrode line in Norway
- 58°10′02″N 8°15′57″E / 58.167183°N 8.265908°E
- 58°10′05″N 8°15′51″E / 58.168114°N 8.264144°E
- 58°10′09″N 8°15′50″E / 58.169155°N 8.263886°E
- 58°10′15″N 8°15′49″E / 58.170929°N 8.263629°E
- 58°10′26″N 8°15′33″E / 58.174004°N 8.259224°E
- 58°10′36″N 8°15′14″E / 58.17672°N 8.253817°E
- 58°10′50″N 8°14′52″E / 58.180674°N 8.247691°E
- 58°10′59″N 8°14′31″E / 58.183106°N 8.241828°E
- 58°11′22″N 8°12′44″E / 58.189412°N 8.212178°E
- 58°11′28″N 8°11′55″E / 58.191072°N 8.198703°E
- 58°11′21″N 8°11′25″E / 58.189212°N 8.190318°E
- 58°11′15″N 8°10′07″E / 58.187493°N 8.168491°E
- 58°11′08″N 8°09′58″E / 58.185459°N 8.166229°E
- 58°11′04″N 8°09′57″E / 58.184441°N 8.165923°E
- 58°10′58″N 8°09′58″E / 58.182720°N 8.165999°E
- 58°11′10″N 8°09′24″E / 58.186074°N 8.156698°E
See also
[edit]- List of high-voltage transmission links in Denmark
- List of high-voltage transmission links in Norway
- Baltic Cable
- Scotland-Norway interconnector
References
[edit]- ^ a b c d e "Skagerrak". ABB. Archived from the original on 2016-01-20. Retrieved 2015-09-09.
- ^ "Skagerrak | References | ABB". new.abb.com. Archived from the original on 2014-05-02.
- ^ a b "The Skagerrak HVDC Scheme". Bonneville Power Administration. Archived from the original on 2005-08-02. Retrieved 2011-02-13.
- ^ "Renovering af HVDC forbindelsen Bulbjerg-Tjele" [Renovation of the HVDC connection Bulbjerg-Tjele]. Archived from the original on 2016-03-06. Retrieved 2016-01-26.
- ^ "Norske kabler mister fire prosent av kraften på vei til Danmark" [Norwegian cables lose four percent of their power on their way to Denmark]. Teknisk Ukeblad. 25 March 2017. Retrieved 10 September 2017.
- ^ "#mensviventer blæses spildvarme ud til fuglene" [while we wait, waste heat is blown out to the birds]. 16 March 2016. Archived from the original on 22 April 2016. Retrieved 26 March 2016.
- ^ Daniel McClane (30 July 2015). "Apple fik rådgivning af den danske stat til at betale mindre skat" [Apple was advised by the Danish state to pay less tax]. Version2.
- ^ "Submarine power cable to connect Jordan, Egypt". PowerGen Worldwide. PennWell Corporation. 1995-01-01. Retrieved 2011-02-13.
- ^ Herse, Erik (18 December 1998). "Rationering af el på vej" [Rationing of electricity on the way]. Ingeniøren (in Danish).
- ^ "Kommersiell drift av SK4 utsatt" [Commercial operation of SK4 postponed]. Statnett. 15 December 2014.
- ^ "Demark, Norway to build fourth interconnector". PowerGen Worldwide. PennWell Corporation. 2009-12-09. Retrieved 2011-02-13.
- ^ "Skagerrak - An excellent example of the benefits that can be achieved through interconnections". new.abb.com. Archived from the original on 2016-01-20.
- ^ Bredsdorff, Magnus. Nytårsblæsevejr: Vindmølleejere betaler for at producere strøm (in Danish) tr. New Year's windy weather: Wind turbine owners pay to produce electricity Ing.dk, 2 January 2015. Accessed: 2 January 2015.
- ^ Lind, Anton. "600 kilometer søkabel skal føre strøm mellem Norge og Danmark" tr. 600 kilometers of submarine cable will carry electricity between Norway and Denmark Danmarks Radio, 12 March 2015. Accessed: 13 March 2015.
- ^ a b Mikkelsen, Søren Damsgaard. Billion kroner cables Archived 2011-07-19 at the Wayback Machine Energinet.dk, 7 January 2011. Accessed: 9 January 2011.
- ^ "ABB wins $180m order for Norway-Denmark power transmission link". PowerGen Worldwide. PennWell Corporation. 2011-02-11. Retrieved 2011-02-13.
- ^ 130 mio. euro for new technology on Skagerrak 4 Archived 2011-02-16 at the Wayback Machine Energinet.dk, 10 February 2011. Accessed: 29 November 2011.
- ^ Godske, Bjørn. New cable to Norway secures grid against faults Archived 2012-10-20 at the Wayback Machine (in Danish) Ing.dk, 11 February 2011. Accessed: 11 February 2011.
- ^ Offentliggørelse af priser for systemydelser på SK4 tr. Publication of prices for system services on SK4 Archived 2016-03-03 at the Wayback Machine Energinet.dk, 1 December 2014. Accessed: 25 February 2016.
- ^ Zachariassen, Espen. "Statnett bør pålegges å legge fiber i utenlandskablene" tr. Statnett should be ordered to lay fiber in the foreign cables Teknisk Ukeblad, 23 October 2013. Accessed: 12 January 2015.
External links
[edit]- Electrical interconnectors to and from the Nordic grid
- Electrical interconnectors to and from the Synchronous Grid of Continental Europe
- Electric power infrastructure in Denmark
- Electric power infrastructure in Norway
- HVDC transmission lines
- Electrical interconnectors in the North Sea
- Denmark–Norway relations
- Energy infrastructure completed in 1977
- Energy infrastructure completed in 1993
- 1977 establishments in Denmark
- 1977 establishments in Norway